USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

FAST-41 Covered Projects Postings by Agencies for Mountain Valley and Equitrans Expansion Project

Application and Supporting Documents

The project sponsor filed an application pursuant to section 7(c) of the Natural Gas Act for a certificate of public convenience and necessity on October 23, 2015. And the project sponsor filed an application to amend its certificate of public convenience and necessity on February 19, 2021. The applications and other supporting documents can be found by searching under docket numbers CP16-10 and CP21-57 in the Commission’s eLibrary system.   

Information on the status of mitigation measures

The Commission issued a certificate and an amended certificate for the project on October 13, 2017, and April 8, 2022, respectively. These orders include appendices specifying environmental conditions, including mitigation measures. The project sponsor has implemented the required environmental conditions to commence project construction. 

Description of the status of any litigation

There is no active litigation on the Commission’s certificate proceedings.

Information about project-related public meetings, public hearings, and public comment periods

The Commission has no planned public meetings, public hearings, or public comment periods. 

Description of any Federal agency action taken or decision made that materially affects the status of the project

The Commission issued a certificate and an amended certificate for the project on October 13, 2017, and April 8, 2022, respectively. Commission staff issued National Environmental Policy Act documents prior to the Commission’s issuance of the certificate and amended certificate for the project, including a Final Environmental Impact Statement under CP16-10 and an Environmental Assessment under CP21-57.