USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Covered Projects Postings by Agencies for Mississippi Crossing Project

Application and Supporting Documents

The project sponsor filed an application under section 7 of the Natural Gas Act on June 30, 2025. The application and other supporting documents can be found under docket number CP25-514 in the Commission's eLibrary system.

Information on the status of mitigation measures

On July 31, 2026, the Commission issued an order authorizing the project, subject to certain environmental conditions.

Description of the status of any litigation

There is no active litigation on the Commission's certificate proceeding.

Information about project-related public meetings, public hearings, and public comment periods

Information on the timing of project-related comment periods and public meetings will be added to this section as it becomes available.

  • On July 15, 2025, the Commission issued a notice with information on how to become involved in the Commission's review process, including filing comments.
  • On September 5, 2025, the Commission issued a notice establishing a deadline for filing comments on the scope of issues to address in the Environmental Impact Statement.
  • On January 30, 2026, the Commission issued a notice with information on submitting written comments and attending public comment sessions on the draft Environmental Impact Statement.
Description of any Federal agency action taken or decision made that materially affects the status of the project