USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

FAST-41 Covered Projects Postings by Agencies for Kulning Wind Energy Project

FAST-41 Initiation Notice

BLM accepted the FIN as lead agency.

Application and Supporting Documents

Project has been cancelled.

Information on the status of mitigation measures

Project has been cancelled.

Description of the status of any litigation

N/A

Information about project-related public meetings, public hearings, and public comment periods

Project has been cancelled.

Description of any Federal agency action taken or decision made that materially affects the status of the project

Project has been cancelled.