FAST-41 Covered Projects Postings by Agencies for Grain Belt Express Transmission - Phase 1

FAST-41 Initiation Notice

The entire FAST-41 Initiation Notice is marked as confidential business information and is therefore not available for public posting.

Application and Supporting Documents

Notice of Intent to Prepare an Environmental Impact Statement for the Grain Belt Express Transmission Line Project, DOE/EIS-0554; and Notice of Floodplain Action | Department of Energy

The Environmental Impact Statement and related documents will be posted on the Department of Energy’s website once they are available.

The Title 17 loan application is marked as confidential business information and is therefore not available for public posting.

Information on the status of mitigation measures

These will be identified in the Draft Environmental Impact Statement.

Description of the status of any litigation

None.

Information about project-related public meetings, public hearings, and public comment periods

The DEIS Public Comment Period is open January 17 to March 3, 2025

DEIS Public Meetings (Central Time) are scheduled as follows:

February 10, 2025 - 4 – 6 p.m., Dodge City Public Library, 1001 N. 2nd Ave., Dodge City, KS 67801

February 11, 2025 - 4 – 6 p.m., Holiday Inn Express, 2175 Lincoln St., Concordia, KS 66901 

February 12, 2025 - 4 – 6 p.m., St. Joseph Museum, Jackie Lewin Conference Roon, 3406 Frederick Ave. St. Joseph, MO 64506 

February 13, 2025 - 4 – 6 p.m., La Bella Casa Event Center, 5 South Main St., Carrollton, MO 64633 

 

Virtual Meetings (Central Time):

February 19, 2025 - 11 a.m. – 1 p.m. 

February 20, 2025 - 4 - 6 p.m.

 

For more information, please visit: EIS-0554: Grain Belt Express Transmission Line | Department of Energy

Description of any Federal agency action taken or decision made that materially affects the status of the project

None at this time.