USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

FAST-41 Covered Projects Postings by Agencies for Bonanza Solar Project

FAST-41 Initiation Notice

FAST-41 Initiation August 13, 2021

 

Application and Supporting Documents

Bonanza Solar, LLC submitted a right-of-way application for the Bonanza Solar Project to the Bureau of Land Management on December 4, 2020. The application indicated that a plan of development, required for right-of-way applications, would be submitted within 60 days of the application filing. A plan of development for the Bonanza Solar Project was submitted on March 5, 2021. The required application fee was paid on May 26, 2021.

For additional information contact the BLM Project Manager.

NEPA: Bonanza Solar Project

Information on the status of mitigation measures

None as of September 8, 2023

Description of the status of any litigation

None as of September 8, 2023

Information about project-related public meetings, public hearings, and public comment periods
Description of any Federal agency action taken or decision made that materially affects the status of the project

The regulations state that the BLM will “Apply screening criteria to prioritize processing of applications with lesser conflicts over applications with greater resource conflicts…” (43 CFR §2804.25(e)(ii)). Regulations further state that “High-priority applications are given processing priority over medium- and low-priority applications…” (43 CFR §2804.35(a)).

The BLM completed the processing priority review of the application, in accordance with the regulations, on September 8, 2021. Due to resource conflicts associated with the project, the Bonanza Solar Project application was categorized as a Medium Priority for processing. The regulations require the BLM to prioritize processing of high priority-lower conflict applications over processing of medium priority applications, like the Bonanza Solar Project application. The prioritization review identified several project conflicts that need to be reviewed further and/or resolved.

NEPA: Bonanza Solar Project