FAST-41 Covered Projects Postings by Agencies for Boardman to Hemingway Transmission Line

FAST-41 Initiation Notice

The FIN will be posted by the Lead Agency.

Application and Supporting Documents

Application and supporting documents are dependent on submittal of a final Plan of Development (POD).  A final, complete POD has not yet been received.  

Information on the status of mitigation measures

Mitigation measures were partially identified in the 2018 Record of Decision.  Final and complete mitigation measures will be dependent on submittal of a final Plan of Development (POD) and application.

Description of the status of any litigation

None.

Information about project-related public meetings, public hearings, and public comment periods

All public engagement is complete as of the 2018 ROD.

Description of any Federal agency action taken or decision made that materially affects the status of the project

Agency action (or decision) is dependent on submittal of a final Plan of Development (POD) and application.