FAST-41 Covered Projects Postings by Agencies for Alaska LNG Project

Application and Supporting Documents

The project sponsor filed an application under section 3 of the Natural Gas Act on April 17, 2017. The application and other supporting documents can be found by searching under docket number CP17-178 in the Commission’s eLibrary system.  

Information on the status of mitigation measures

The Commission issued an order authorizing the project on May 21, 2020. The order includes an appendix specifying environmental conditions, including mitigation measures.

Description of the status of any litigation

There is no active litigation on the Commission’s proceeding for the project.

Information about project-related public meetings, public hearings, and public comment periods

The Commission has no planned public meetings, public hearings, or public comment periods.

Description of any Federal agency action taken or decision made that materially affects the status of the project

The Commission issued an order authorizing the project on May 21, 2020. Pursuant to the National Environmental Policy Act, Commission staff prepared both Draft and Final Environmental Impact Statements prior to the Commission’s issuance of the order authorizing the project.