The project sponsor filed an application under section 3 of the Natural Gas Act on April 17, 2017. The application and other supporting documents can be found by searching under docket number CP17-178 in the Commission’s eLibrary system.
The Commission issued an order authorizing the project on May 21, 2020. The order includes an appendix specifying environmental conditions, including mitigation measures.
There is no active litigation on the Commission’s proceeding for the project.
The Commission has no planned public meetings, public hearings, or public comment periods.