Pausing Projects
Projects on the Permitting Dashboard can be “Paused” in situations where the lead agency cannot determine new milestone dates due to reasons beyond the government’s control and progress is suspended on all actions for that project. For example, a project would be appropriately “Paused” if the project sponsor notifies the lead agency that they are changing the scope of the project.
In the case of a project pause, the lead agency would first mark all actions as “Paused,” then change the overall project status to “Paused” and indicate the reason for pause (e.g., “Project Sponsor Factors”). When marking a project as “Paused,” the reason for pause must be selected from one of the reasons in following list. The table below includes a non-exhaustive list of scenarios for each reason for pause. If you have questions about which scenario is applicable to your project, please contact the appropriate FAST-41, OMB, or DOT point of contact.
After selecting a reason for pause, the lead agency must provide a short summary of the steps that are being taken to determine a new project timetable and an estimate of when the pause will be lifted. The short summary must include descriptions of coordination with the project sponsor and potentially affected agencies, whether the appropriate agency CERPOs have been made aware of the pause, and next steps in resolving the project schedule. While the project is in “Paused” status, this summary must be updated at least quarterly.
Once the lead agency receives sufficient information to revise the project timetable, the agency should change the status of all actions back to “In Progress,” update the relevant milestone target dates, and list the reason for date change as “Project pause.” For FAST-41 projects, updates to milestone target completion dates will trigger the Executive Director review process for the scenarios described in the FAST-41 Data Management Guides.
Reason for Pause |
Possible Scenarios or Examples |
---|---|
State Government Factors |
|
Local Government Factors |
|
Tribal Government Factors |
|
Project Sponsor Factors |
|
Pending Legal Action |
|
Natural Disasters |
|