Section 106 Review

Project Name: Hudson Tunnel Project
Target Completion: 
03/30/2018
Status: 
In Progress
Responsible Agency: 
States
Reason(s): 
Milestones:
Initial application received
Complete 05/12/2016
Target: 05/12/2016
Completed application received
Complete 07/07/2017
Target: 06/30/2017
Issuance of decision for permit/approval.
Planned
Target: 03/30/2018
Notice to proceed
Planned
Target: 03/30/2018
Review Terminated with no decision