Right-of-Way Authorization (BOR)

Project Name: Transwest Express
Target Completion: 
07/17/2017
Status: 
Complete
Responsible Agency: 
Bureau of Reclamation
Agency Status: 
Cooperating under FAST-41
Cooperating under NEPA
Reason(s): 
Description: 

The Reclamation ROD was finalized July 15 2017. The Reclamation license was issued July 6, 2017.

Milestones:
Initial application received
This milestone was completed prior to initiation as an existing covered project.
Complete
Completed application received
N/A
Issuance of decision for permit/approval.
Complete 07/06/2017
Target: 07/17/2017
Notice to proceed
Review Terminated with no decision