USA logoAn Official Website of the United States Government

You are here

Swan Lake North Pumped Storage

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.


PROJECT STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE
SUBJECT TO CHANGE
4 OUT OF 7
ENVIRONMENTAL REVIEW
AND PERMITTING PROCESSES COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Description: 

Swan Lake North Pumped Storage (Project No. 13318) is a proposal to construct an original, closed-loop pumped storage project that would provide 393 MW of generation capacity in Oregon.  The proposed project would consist of, among other facilities, an upper and lower reservoir with active storage capacities of 2,562 and 2,581 acre-feet, respectively, a high-pressure penstock, three low-pressure penstocks, a powerhouse, a substation, and a 32.8-mile-long, 230-kilovolt transmission line. 

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

Last updated June 27, 2019

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.

To view Timetable chart, please turn device sideways (landscape)

Overall Project Timetable
STATUS
Schedule
Extension
Ahead of Schedule
Paused

*Planned dates are not represented in the timetable above.

Action Information

For additional information, please select an Action from the Permitting Timetable above.

Action:
Responsible Agency:
Bureau:
Action Status:
SHPO:
Action Identifier:
Action Outcome:
Milestone
Original Target Date
Current Target Date
Milestone Complete