PennEast Pipeline

PROJECT WEBSITE: http://penneastpipeline.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.


PROJECT STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE
SUBJECT TO CHANGE
4 OUT OF 7
ENVIRONMENTAL REVIEW
AND PERMITTING PROCESSES COMPLETED
SECTOR
Pipelines
CATEGORY
FAST-41 Covered Projects
LEAD AGENCY
Federal Energy Regulatory Commission
Description: 

PennEast Pipeline (Docket No. CP15-558-000) would provide an additional 1.0 Bcf/d of natural gas transportation service through construction of:  (1) 115.1 miles of pipeline from Pennsylvania to New Jersey; (2) 2.1 miles of various lateral pipelines; and (3) a new compressor station.

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.
State Agency Permitting Timetable for the PennEast Pipeline Project 
Responsible State AgencyFederal Permit/ReviewIntermediate Completion DateFinal Completion DateDescription Field
Pennsylvania Department of Environmental ProtectionSection 401 CWA Review - Water Quality CertificationN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
New Jersey Department of Environmental Protection, Division of Land Use RegulationSection 401 CWA Review - Water Quality CertificationN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  The final completion date is unavailable until site access is acquired, site surveys are completed, and an application is submitted by the project sponsor.  
New Jersey Department of Environmental Protection, Division of Land Use RegulationSection 402 CWA Review - National Pollutant Discharge Elimination System, Stormwater General PermitN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  The final completion date is unavailable until site access is acquired, site surveys are completed, and an application is submitted by the project sponsor.  
Pennsylvania Department of Environmental ProtectionSection 402 CWA Review - National Pollutant Discharge Elimination System, Hydrostatic Test Discharge PermitN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
New Jersey Department of Environmental Protection, Division of Land Use RegulationClean Water Act Section 404 PermitN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  The final completion date is unavailable until site access is acquired, site surveys are completed, and an application is submitted by the project sponsor.  
Pennsylvania Department of Environmental ProtectionTitle V CAA Review - Operating Permit for Air EmissionsN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable. 18 C.F.R. § 157.22 (2016) provides that "a final decision on a request for a Federal authorization is due no later than 90 days after the Commission issues its final environmental document, unless a schedule is otherwise established by Federal law."
New Jersey Department of Environmental Protection, Division of Air QualityTitle V CAA Review - Operating Permit for Air EmissionsN/ATBDThe state agency has not opted into the FAST-41 process.  This authorization is listed for information purposes only, and does not transfer any responsibility to the state agency to conform to the Permitting Timetable.  The final completion date is unavailable until site access is acquired, site surveys are completed, and an application is submitted by the project sponsor.  

 

Last updated June 28, 2019

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.

To view Timetable chart, please turn device sideways (landscape)

Overall Project Timetable
STATUS
Schedule
Extension
Ahead of Schedule
Paused

Action Information

For additional information, please select an Action from the Permitting Timetable above.

Action:
Responsible Agency:
Bureau:
Action Status:
SHPO:
Action Identifier:
Action Outcome:
Milestone
Original Target Date
Current Target Date
Milestone Complete