Reach 12 Tohlakai Pumping Plant Right of Way for Construction on Tribal Fee Land

Status: 
Complete
Responsible Entity: 
Responsible Agency POC: 
Jason John
Branch Manager, The Navajo Nation Department of Water Resources
Project: 
Navajo Gallup Water Supply Project
Type: 
Ad Hoc Activity
Reach 12 Tohlakai Pumping Plant is located on the western, "San Juan Lateral" portion of the project. In order to award a construction contract for construction Reclamation must be granted permanent right of way and construction easements for all required property. Reclamation has worked with the Navajo Nation to obtain these documents on the Navajo Nation Tribal Fee Lands. Reclamation has coordinated and built relationships with the Navajo Nation to emphasize the high priority nature of the project and to expedite the Navajo Nations approval for consent process. Reclamation is working with the Navajo Nation to develop an expedited approval process on the remaining construction reaches for the project.

Milestones

Milestone Target Actual
Milestone Start - Reach 12 Tohlakai Pumping Plant Right of Way for Construction on Tribal Fee Land 01/23/2013 01/23/2013
Milestone End - Reach 12 Tohlakai Pumping Plant Right of Way for Construction on Tribal Fee Land 02/05/2014 01/30/2014