Project: 
NextGen Infrastructure Initiative - Houston Metroplex (OAPM)
Type: 
Ad Hoc Activity
This phase includes all steps required for implementation of the metroplex optimization project including flight checks, procedure publication, airspace modifications and training. The regional Flight Procedures Team is heavily involved in this phase. The target date for publication of the Houston metroplex optimized procedures is December 12, 2013.

Milestones

Milestone Target Actual
Milestone Start - Implementation 01/10/2013 01/10/2013
Milestone End - Implementation 05/28/2014 05/28/2014