ACFS/SDFP: Biological Opinion - National Marine Fisheries Service

Status: 
Complete
Responsible Entity: 
Responsible Agency POC: 
Rhonda Reed
Program Director, San Joaquin River Basin
Project: 
San Joaquin River Restoration Program - Arroyo Canal Fish Screen & Sack Dam Fish Passage Project
Type: 
Ad Hoc Activity
NOAA's National Marine Fisheries Service will prepare a Biological Opinion and based on the Bureau of Reclamation's Biological Assessment for species listed under the Endangered Species Act and/or the Magnuson Stevens Fishery Conservation and Management Act for Essential Fish Habitat (Conservation Recommendation).

Milestones

Milestone Target Actual
Milestone Start - ACFS/SDFP: Biological Opinion - National Marine Fisheries Service 05/24/2012 05/24/2012
Milestone End - ACFS/SDFP: Biological Opinion - National Marine Fisheries Service 08/30/2013 08/29/2013