ACFS/SDFP: Biological Assessment

Status: 
Complete
Responsible Entity: 
Responsible Agency POC: 
Alicia Forsythe
Program Manager, San Joaquin River Restoration Program
Project: 
San Joaquin River Restoration Program - Arroyo Canal Fish Screen & Sack Dam Fish Passage Project
Type: 
Ad Hoc Activity
The Bureau of Reclamation will submit a Biological Assessment to the U.S. Fish and Wildlife Service and National Marine Fisheries Service to initiate consultation under Section 7 of the Endangered Species Act (ESA). This document will address species listed under the ESA, Migratory Bird Treaty Act, and include a request for consultation on the Magnuson Stevens Fishery Conservation and Management Act for Essential Fish Habitat.

Milestones

Milestone Target Actual
Milestone Start - ACFS/SDFP: Biological Assessment 11/01/2011 11/01/2011
Milestone End - ACFS/SDFP: Biological Assessment 05/23/2012 05/23/2012