60 Governor's Consistency Review for the proposed Land Use Plan amendment

Status: 
Complete
Responsible Entity: 
Responsible Agency POC: 
Eddie Arreola
RECO Supervisor
Project: 
Quartzsite Solar Energy Project
Type: 
Ad Hoc Activity
The Governor's office is allowed 60 days to review the proposed amendment to the Resource Management Plan to determine if and how that amendment may affect the State's planning efforts.

Milestones

Milestone Target Actual
Milestone Start - 60 Governor's Consistency Review for the proposed Land Use Plan amendment 11/22/2012 12/25/2012
Milestone End - 60 Governor's Consistency Review for the proposed Land Use Plan amendment 02/27/2013 02/24/2013