National Environmental Policy Act (NEPA)

Status: 
Complete
Responsible Entity: 
Responsible Agency POC: 
Eddie Arreola
RECO Supervisor
Project: 
Quartzsite Solar Energy Project
Type: 
Standard Permit
NEPA requires Federal agencies to consider the potential environmental consequences of their actions before deciding whether and how to take the action. The CEQ Regulations established three forms of review that Federal agencies use to comply with NEPA and those are the Categorical Exclusion, an Environmental Assessment (EA), or an Environmental Impact Statement (EIS).

Milestones

Milestone Target Actual
Milestone Start - National Environmental Policy Act (NEPA) 01/13/2010 01/13/2010
Milestone End - National Environmental Policy Act (NEPA) 05/28/2013 06/02/2013