Public and agency review of EA

Status: 
Complete
Responsible Entity: 
DOT
Responsible Agency POC: 
Colleen Vaughn
Project: 
Point Defiance Bypass
Type: 
Public Participation Activity
A public information meeting and hearing are scheduled on October 24 and 25th respectively to gather comment on the proposed project

Milestones

Milestone Target Actual
Milestone Start - Public and agency review of EA 10/14/2012 10/07/2012
Milestone End - Public and agency review of EA 10/25/2012 11/08/2012