Enterprise WEP III - Mid America Pipeline (MAPL)

Project Information
Sector: 
Pipelines
Status: 
Complete
Total Estimated Project Cost: 
$320,000,000
Description: 
This proposed project consists of an approximately 246-mile long 16-inch or 20-inch natural gas liquids pipeline consisting of seven segments all located within New Mexico. The proposed pipeline loop segments would transport increased natural gas liquids production in New Mexico to Hobbs, New Mexico and ultimately to markets in Mont Belvieu, Texas, helping to meet existing and future energy demand.

Reviews, Approvals and Permits

Titlesort descending Responsible Agency Responsible Agency POC Target Completion Date Status
Agencies Review of Final Cultural Report Dave Simons 7/30/2013 Complete
Agency Review of Project Lorraine Salas 11/28/2013 Planned
Biological and Wetland Surveys Lorraine Salas 10/30/2012 Complete
BLM & Enterprise MAPL Project Introduction Kick-off Meeting Lorraine Salas 7/19/2012 Complete
BLM - Notice to Proceed Lorraine Salas 7/31/2013 Planned
BLM Consultation with Agencies Lorraine Salas 7/31/2013 Complete
BLM issues MLA Grant Lorraine Salas 6/13/2013 Complete
Construction Phase Lorraine Salas 11/28/2013 Planned
Cultural Resources Survey Dave Simons 11/29/2012 Complete
Determination of NEPA Analysis Lorraine Salas 8/23/2012 Complete