USA logoAn Official Website of the United States Government

You are here

Enterprise WEP III - Mid America Pipeline (MAPL)

Project Information
Sector: 
Pipelines
Status: 
Complete
Total Estimated Project Cost: 
$320,000,000
Description: 
This proposed project consists of an approximately 246-mile long 16-inch or 20-inch natural gas liquids pipeline consisting of seven segments all located within New Mexico. The proposed pipeline loop segments would transport increased natural gas liquids production in New Mexico to Hobbs, New Mexico and ultimately to markets in Mont Belvieu, Texas, helping to meet existing and future energy demand.

Reviews, Approvals and Permits

Title Responsible Agency Responsible Agency POC Target Completion Date Statussort descending
Draft Supplemental Cultural Inventory Report Dave Simons 12/30/2012 Cancelled
Draft Supplemental Cultural Report Dave Simons 1/31/2013 Cancelled
Draft Supplemental Cultural Report Dave Simons 4/17/2013 Cancelled
Final Supplemental Cultural Report Dave Simons 5/06/2013 Cancelled
Programmatic Agreement for compliance with NHPA State or Local Agency, DOI Dave Simons 7/18/2013 Complete
Cultural Resources Survey Dave Simons 11/29/2012 Complete
Draft Cultural Report Dave Simons 10/31/2012 Complete
Draft Cultural Report Dave Simons 11/29/2012 Complete
Agencies Review of Final Cultural Report Dave Simons 7/30/2013 Complete
Final Cultural Report Dave Simons 3/14/2013 Complete