USA logoAn Official Website of the United States Government

You are here

Enterprise WEP III - Mid America Pipeline (MAPL)

Project Information
Sector: 
Pipelines
Status: 
Complete
Total Estimated Project Cost: 
$320,000,000
Description: 
This proposed project consists of an approximately 246-mile long 16-inch or 20-inch natural gas liquids pipeline consisting of seven segments all located within New Mexico. The proposed pipeline loop segments would transport increased natural gas liquids production in New Mexico to Hobbs, New Mexico and ultimately to markets in Mont Belvieu, Texas, helping to meet existing and future energy demand.

Reviews, Approvals and Permits

Title Responsible Agency Responsible Agency POC Target Completion Datesort descending Status
BLM & Enterprise MAPL Project Introduction Kick-off Meeting Lorraine Salas 7/19/2012 Complete
Purpose and Need Lorraine Salas 7/30/2012 Complete
Determination of NEPA Analysis Lorraine Salas 8/23/2012 Complete
Tribal Consultation - Invitation for Consultation Dave Simons 9/05/2012 Complete
Paleontological Surveys Sherrie Landon 10/30/2012 Complete
Biological and Wetland Surveys Lorraine Salas 10/30/2012 Complete
Public Involvement Plan Lorraine Salas 10/30/2012 Complete
Draft Cultural Report Dave Simons 10/31/2012 Complete
Public Scoping Period Lorraine Salas 11/14/2012 Complete
Cultural Resources Survey Dave Simons 11/29/2012 Complete