USA logoAn Official Website of the United States Government

You are here

Chokecherry-Sierra Madre Wind Energy

Project Information
Sector: 
Renewable Energy
Status: 
In Progress
Description: 

The Chokecherry Sierra Madre (CCSM) Wind Energy Project is a two phase development which proposes to build 1,000 wind turbines on 219,707 acres in Carbon County, Wyoming.  Early coordination has resulted in numerous mutually-agreed upon wildlife monitoring practices that will improve the siting of wind turbines. Additionally, the project proponent has significantly modified its proposed action to take into account issues raised by the public with regards to potential conflicts with other resource uses in the area. Once completed, the project will have the capacity to generate up to 3,000 megawatts of clean, renewable power -- enough to run nearly 1 million homes.

The programmatic Record of Decision (ROD) was signed October 2012 that determines that wind energy development is appropriate within a portion of the 219,707-acre conceptual area of development for the CCSM Project.   An Environmental Assessment for Infrastructure Components (EA1) and Decision Record (DR) on the Phase I Haul Road and Facilities, Road Rock Quarry and West Sinclair Rail Facility was signed by the Department of the Interior (DOI) Assistant Secretary for Land and Minerals Management on Dec. 23, 2014.  The decision was later amended in May 2016.  This amendment provided management flexibility to issue multiple right-of-way grants as provided for by the CCSM ROD.  ROW grants were issued for the Infrastructure Components and construction commenced in August 2016. The Bureau of Land Management (BLM) released the Phase I Wind Turbine Development Draft Environmental Assessment (EA2) (first 500 wind turbines) and Draft Finding of No New Significant Impacts (FONNSI) in March 2016, prepared consistent with the tiering procedures outlined in the ROD for the CCSM Wind Energy Project. After reviewing public comments, the BLM completed the environmental analysis and signed a Decision Record approving the turbine development on January 17, 2017. The Fish and Wildlife Service (FWS) also completed an Environmental Impact Statement (DEIS) for an Eagle Take Permit for the project on December 9, 2016.  The BLM anticipates finalize the ROW in March, 2017. The BLM will initiate the permitting for Phase 2 once the project sponsor has submitted the application.

Additional information is available on the project website at:

http://www.blm.gov/wy/st/en/info/NEPA/documents/rfo/Chokecherry.html

Or on the ePlanning website at:

https://eplanning.blm.gov/epl-front-office/eplanning/planAndProjectSite.do?methodName=renderDefaultPlanOrProjectSite&projectId=58548

Reviews, Approvals and Permits

Title Responsible Agency Responsible Agency POC Target Completion Datesort descending Status
Project Scoping Pam Murdock 3/31/2008 Complete
Preliminary Draft EIS Pam Murdock 7/31/2008 Complete
DEIS Review by WO Pam Murdock 6/12/2011 Complete
Publish NOA for DEIS Pam Murdock 7/21/2011 Complete
BLM SO review of PFEIS Pam Murdock 3/11/2012 Complete
PFEIS Review by WO Pam Murdock 4/15/2012 Complete
Publish NOA for FEIS Pam Murdock 6/28/2012 Complete
Protest Period Pam Murdock 7/29/2012 Complete
Publish ROD Pam Murdock 9/26/2012 Complete
ESA Section 7 Consultation Nathan Darnall 9/27/2012 Complete
Submit Feedback >