ESA Section 7 Consultation

Status: 
Complete
Responsible Entity: 
Responsible Agency POC: 
Nathan Darnall
Project: 
Chokecherry-Sierra Madre Wind Energy
Type: 
Ad Hoc Activity
Review and edit the draft biological assessment (up to 30 days). Once FWS has a final biological assessment with complete information, FWS has up to 135 days to complete the biological opinion. We expect the consultation will be completed well under the full 135 days.

Milestones

Milestone Target Actual
Milestone Start - ESA Section 7 Consultation 07/01/2012 07/01/2012
Milestone End - ESA Section 7 Consultation 09/27/2012 09/04/2012