Water Quality Certification

Status: 
Complete
Responsible Entity: 
Responsible Agency POC: 
Kevin Rose
Environmental Compliance Team Leader
Project: 
Dredge Sailors Haven, Talisman-Barrett Beach and Watch Hill Channels and Marinas
Type: 
Standard Permit
Under Clean Water Act 401, a federal agency cannot issue a permit or license for an activity that may result in a discharge to waters of the U.S. until the state or tribe where the discharge would originate has granted or waived 401 certification. All states, territories and more than 36 tribes have 401 certification, but in instances where the discharge originates within a jurisdiction without 401 authority, EPA is the certifying agency.

Milestones

Milestone Target Actual
Milestone Start - Water Quality Certification 02/10/2014 02/10/2014
Milestone End - Water Quality Certification 09/21/2014 09/23/2014