RM 2222

PROJECT WEBSITE: TxDOT Inside TxDOT Projects

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/04/2018

3 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

States icon

LEAD AGENCY
States, Texas

Description:

The project consists of adding an outside lane on northbound RM 620 from Steiner Ranch Boulevard to before the RM 2222/Bullock Hollow intersection. The new proposed bypass road would then be constructed from RM 620 along the LCRA electrical transmission line right-of-way to intersect RM 2222. At this location, an additional travel lane would be added to both sides of RM 2222 to move the traffic past the Vandegrift High School entrance on McNeil Road.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete