MARTA Clifton Road Transit Initiative

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused icon

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Surface Transportation icon

SECTOR
Surface Transportation

CATEGORY
DOT Projects

Department of Transportation icon

LEAD AGENCY
Department of Transportation, Federal Transit Administration

Description:

The Metropolitan Atlanta Rapid Transit Authority (MARTA) proposes to create light rail service between the existing Lindbergh and Avondale Stations. This service would connect the major job destinations of the US Centers for Disease Control and Emory University & Hospital to the MARTA rail system. The Clifton Corridor is the largest employment center not served by the MARTA rail system or other high capacity mode of transportation. Currently, significant volumes of trips travel through the Clifton Corridor as well as on connecting roadways; therefore, high-capacity transit service could help accommodate the high trip volumes within an already constrained roadway network.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete