Durham-Orange Light Rail Transit Supplemental Environmental Assessment
PROJECT WEBSITE: Durham-Orange Light Rail Transit Supplemental Environmental Assessment
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
CANCELLED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
N/A
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Transit Administration
Description:
On August 9, 2019, GoTriangle made a determination to discontinue the project and requested FTA withdraw the project from the Capital Investment Grants Program.
GoTriangle is proposing to refine the design of the Durham-Orange Light Rail Transit (D-O LRT) Project, located in Durham and OrangeCounties, North Carolina. This Supplemental Environmental Assessment (Supplemental EA) evaluates proposed refinements to the D-O LRT Project design since the Amended Record of Decision (Amended ROD) was issued December 2016.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|