Dublin Blvd - North Canyons Pkwy Extension
PROJECT WEBSITE: http://dublin.ca.gov/1919/Dublin-Boulevard-Extension
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
DOT Projects

LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:

California
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Description:
The City of Dublin is proposing a project to extend Dublin Blvd from it's existing terminus at Fallon Road in the City of Dublin, to the west end of North Canyons Parkway at Doolan Road in the City of Livermore, Alameda County, California. The project is proposed as an approximate 1.5 mile long, 4- to 6-lane major arterial roadway with bike lanes, sidewalks, curb and gutter, traffic signals, street lighting, landscaped raised median islands, bus stops, and all city street utilities.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|