USA logoAn Official Website of the United States Government

You are here

Chokecherry-Sierra Madre Wind Energy (Phase 1)

Project Information
Sector: Renewable Energy Production
Project Category: 
FAST-41 Covered Projects
Project Status: 
Complete
Description: 

The first phase of the Chokecherry Sierra Madre (CCSM) Wind Energy Project  proposes to build 500 wind turbines in Carbon County, Wyoming.  Early coordination has resulted in numerous mutually-agreed upon wildlife monitoring practices that will improve the siting of wind turbines. Additionally, the project proponent has significantly modified its proposed action to take into account issues raised by the public with regards to potential conflicts with other resource uses in the area. Once completed, the project will have the capacity to generate up to 1,500 megawatts of clean, renewable power -- enough to run nearly 500,000 homes.

The programmatic Record of Decision (ROD) was signed October 2012 that determines that wind energy development is appropriate within a portion of the 219,707-acre conceptual area of development for the CCSM Project.   An Environmental Assessment for Infrastructure Components (EA1) and Decision Record (DR) on the Phase I Haul Road and Facilities, Road Rock Quarry and West Sinclair Rail Facility was signed by the Department of the Interior (DOI) Assistant Secretary for Land and Minerals Management on Dec. 23, 2014.  The decision was later amended in May 2016.  This amendment provided management flexibility to issue multiple right-of-way grants as provided for by the CCSM ROD.  ROW grants were issued for the Infrastructure Components and construction commenced in August 2016. The Bureau of Land Management (BLM) released the Phase I Wind Turbine Development Draft Environmental Assessment (EA2) and Draft Finding of No New Significant Impacts (FONNSI) in March 2016, prepared consistent with the tiering procedures outlined in the ROD for the CCSM Wind Energy Project. After reviewing public comments, the BLM completed the environmental analysis and signed a Decision Record approving the turbine development on January 17, 2017. The Fish and Wildlife Service (FWS) also completed an Environmental Impact Statement (FEIS) for the project on December 9, 2016.

Additional information is available on the ePlanning website at:

https://eplanning.blm.gov/epl-front-office/eplanning/planAndProjectSite.do?methodName=renderDefaultPlanOrProjectSite&projectId=58548

Permitting Timeline

Environmental Impact Statement (EIS)
Bureau of Land Management
Complete
Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS)
Complete 07/25/2008
Target: 07/25/2008
Scoping
Complete 08/29/2008
Target: 08/29/2008
Official Notice of Availability of a Draft EIS published in the Federal Register
Complete 07/21/2011
Target: 07/21/2011
Official Notice of Availability of a Final EIS published in the Federal Register
Complete 06/28/2012
Target: 06/28/2012
Official Notice of Availability of a Supplemental Draft EIS published in the Federal Register
N/A
Official Notice of Availability of a Supplemental Final EIS published in the Federal Register
N/A
Issuance of Record of Decision or combined Final EIS / Record of Decision
Complete 10/08/2012
Target: 09/26/2012
Issuance of an Amended Record of Decision
Environmental Assessment (EA)
Bureau of Land Management
Complete
Milestones:
Determination to prepare an Environmental Assessment (EA)
Release for Public Review
Draft EA or other means of coordinating the development of an EA
Final EA
Draft proposed Finding of No Significant Impact (FONSI)
Issuance of Final EA and Finding of No Significant Impact (FONSI)
Complete 12/23/2014
Decision to prepare an Environmental Impact Statement
Issuance of Supplemental EA
Issuance of Supplemental FONSI
Environmental Assessment (EA)
Bureau of Land Management
Complete
Milestones:
Determination to prepare an Environmental Assessment (EA)
Complete
Release for Public Review
Complete
Draft EA or other means of coordinating the development of an EA
Final EA
Draft proposed Finding of No Significant Impact (FONSI)
Issuance of Final EA and Finding of No Significant Impact (FONSI)
Complete 01/17/2017
Decision to prepare an Environmental Impact Statement
Issuance of Supplemental EA
Issuance of Supplemental FONSI
Right-of-Way Authorization (DOI-BLM)
Bureau of Land Management
07/20/2017
Complete 07/14/2017
Milestones:
Initial application received
Complete 01/30/2008
Target: 01/30/2008
Completed application received
N/A
Issuance of decision for permit/approval.
Complete 07/20/2017
Target: 07/14/2017
Notice to proceed
N/A
Review Terminated with no decision
N/A
Environmental Impact Statement (EIS)
Fish and Wildlife Service
07/14/2015
Complete 12/09/2016
Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS)
Complete 08/04/2013
Target: 04/29/2013
Scoping
Official Notice of Availability of a Draft EIS published in the Federal Register
Complete 12/09/2014
Official Notice of Availability of a Final EIS published in the Federal Register
Official Notice of Availability of a Supplemental Draft EIS published in the Federal Register
N/A
Official Notice of Availability of a Supplemental Final EIS published in the Federal Register
N/A
Issuance of Record of Decision or combined Final EIS / Record of Decision
Complete 12/09/2016
Target: 07/14/2015
Issuance of an Amended Record of Decision
N/A
Bald and Golden Eagle Protection Permit
Fish and Wildlife Service
12/29/2017
Milestones:
Initial application received
Complete
Completed application received
N/A
Target: 11/30/2017
Issuance of decision for permit/approval.
Target: 12/29/2017
Notice to proceed
Review Terminated with no decision
Endangered Species Act Consultation - FWS
Fish and Wildlife Service
09/27/2012
Complete
Milestones:
Date of Request for formal consultation received
Complete 07/01/2012
Target: 07/01/2012
Consultation Initiation Date
Complete
Final Biological Opinion Issued
Complete 09/04/2012
Target: 09/27/2012
Section 106 Review
Wyoming (Cooperating under NEPA)
Complete
Milestones:
Initial application received
Complete 07/25/2008
Target: 07/25/2008
Completed application received
N/A
Issuance of decision for permit/approval.
Complete 11/18/2014
Target: 11/18/2014
Notice to proceed
N/A
Review Terminated with no decision
N/A
Submit Feedback >