5/56 Missing Connection

Project Information
Sector: Surface Transportation
Project Category: 
DOT Projects
Project Status: 
Complete
Total Estimated Project Cost: 
$224,777,000
Description: 

A proposed project to address regional mobility between southbound Interstate 5 (I-5) and eastbound State Route 56 (SR 56) and westbound SR 56 and northbound I-5. Alternatives have been developed to be sensitive to the community and environment, while addressing regional connectivity and local congestion.

Permitting Timeline

Environmental Impact Statement (EIS)
California
Complete
Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) 
Complete 04/20/2005
Scoping 
Complete 12/22/2006
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review
Complete 05/18/2012
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review 
Complete 07/14/2017
Issuance of Record of Decision or combined Final EIS / Record of Decision 
Complete 09/07/2017
Endangered Species Act Consultation (DOI-FWS)
Fish and Wildlife Service
Complete
Milestones:
Request for ESA Consultation Received
Complete 09/28/2011
Conclusion of ESA Consultation
Complete 10/05/2011
Section 106 Review
California
Complete
Milestones:
Consultation initiated with SHPO/THPO
Complete 10/25/2011
Section 106 consultation concluded
Complete 02/02/2012