METRO Blue Line Extension (Bottineau Light Rail Transit)
PROJECT WEBSITE: MetCouncil Bottineau Project webpage
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/24/2018
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
DOT Projects

LEAD AGENCY
Department of Transportation, Federal Transit Administration
Other Agencies with Actions or Authorizations:
Department of Defense

Department of Transportation
Department of the Interior, Fish and Wildlife Service

Minnesota
Description:
The Metropolitan Council has proposed the Bottineau Light Rail Transit project to extend the METRO Blue Line (Hiawatha LRT) by approximately 13 miles. It would operate from downtown Minneapolis through the communities of Golden Valley, Robbinsdale, Crystal, and Brooklyn Park. The proposed alignment includes 11 new light rail stations, approximately 1,670 additional park-and-ride spaces, accommodations for passenger drop-off, and bicycle and pedestrian access, as well as new or restructured local bus route connections to nearby residential, commercial, and educational land uses.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
Milestone | Original Target Date | Current Target Date | Milestone Complete |
---|