Environmental Impact Statement (EIS)

Project Name: 
Status: 
In Progress
Responsible Agency: 
Federal Energy Regulatory Commission
Reason(s): 
Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS)
Complete 05/01/2017
Scoping
Complete 05/01/2017
Official Notice of Availability of a Draft EIS published in the Federal Register
This estimated timeframe is subject to change based on the scope and complexity of the project, the information and resources available to each participating/cooperating agency, the significance of the project's effects and the sensitivity of the natural or historic resources that may be affected by the project, which will become known upon receipt of outstanding information requests.
In Progress
Target: 03/31/2019
Official Notice of Availability of a Final EIS published in the Federal Register
This estimated timeframe is subject to change based on the appropriate time to meet with tribes in consideration of subsistence windows, and the scope and complexity of the project, the information and resources available to each participating/cooperating agency, the significance of the project's effects and the sensitivity of the natural or historic resources that may be affected by the project, which will become known upon receipt of outstanding information requests.
In Progress
Target: 12/09/2019
Official Notice of Availability of a Supplemental Draft EIS published in the Federal Register
N/A
Official Notice of Availability of a Supplemental Final EIS published in the Federal Register
N/A
Issuance of Record of Decision or combined Final EIS / Record of Decision
The Commission is in the process of developing a target completion date for this milestone. Once publicly available, it will be published by Commission staff on the Permitting Dashboard.
In Progress
Issuance of an Amended Record of Decision
N/A