Environmental Impact Statement (EIS)

Description: 

EIS for Chokecherry Sierra Madre (CCSM) Wind Energy Project 

Milestones:
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS)
Complete 07/25/2008
Target: 07/25/2008
Scoping
Complete 08/29/2008
Target: 08/29/2008
Official Notice of Availability of a Draft EIS published in the Federal Register
Complete 07/21/2011
Target: 07/21/2011
Official Notice of Availability of a Final EIS published in the Federal Register
Complete 06/28/2012
Target: 06/28/2012
Official Notice of Availability of a Supplemental Draft EIS published in the Federal Register
N/A
Official Notice of Availability of a Supplemental Final EIS published in the Federal Register
N/A
Issuance of Record of Decision or combined Final EIS / Record of Decision
Complete 10/08/2012
Target: 09/26/2012
Issuance of an Amended Record of Decision