Consultation to Protect Essential Fish Habitat

Status: 
Complete
Responsible Agency: 
National Oceanic and Atmospheric Administration
Agency Status: 
Cooperating under NEPA
Reason(s): 
Description: 

Essential Fish Habitat (EFH) consultation.

Milestones:
Initial application received
NMFS consulted twice on this project. The initial request was on 01/25/16, and the second request was on 06/02/16 (for the Alternative 5 revisions).
Complete 01/25/2016
Completed application received
NMFS consulted twice on this project. The initial request was on 01/25/16, and the second request was on 06/02/16 (for the Alternative 5 revisions).
Complete 01/25/2016
Issuance of decision for permit/approval.
NMFS issued a final response to the initial request for consultation on 04/14/16. No EFH Conservation Recommendations were needed. NMFS issued a final response to the second request for consultation (Alt 5) on 08/19/16. No EFH Conservation Recommendations were needed.
Complete 04/14/2016
Notice to proceed
N/A
Review Terminated with no decision
N/A