Bald and Golden Eagle Protection Permit

Description: 

Eagle Take Permit application for Phase 1 of the Chokecherry Sierra Madre Wind Energy Project

Milestones:
Initial application received
Complete
Completed application received
Planned
Target: 11/30/2017
Issuance of decision for permit/approval.
This milestone is contingent upon receipt of the final, signed mitigation plan. FWS met with the sponsor on October 30, 2017 to discuss the latest version of the draft power pole retrofit/mitigation plan. As of December 15, 2017, FWS had not received the revised power pole retrofit/mitigation plan. In addition, sponsor needs to have the final mitigation plan signed by the power line company and that had not occurred as of October 30, 2017. FWS will issue the Eagle Take Permit within 30 days of receiving the final power pole retrofit/mitigation plan.
Paused
Target: 12/29/2017
Notice to proceed
Review Terminated with no decision