Bald and Golden Eagle Protection Permit

Description: 

The Eagle Take Permit application for Phase 1 of the Chokecherry Sierra Madre Wind Energy Project is voluntary, and FWS is currently consulting with the applicant on the ideal timing for the permit, which will be issued after construction was initiated.

Milestones:
Initial application received
This milestone was completed prior to initiation under FAST-41.
Complete
Completed application received
N/A
The Eagle Take Permit application for Phase 1 of the Chokecherry Sierra Madre Wind Energy Project is voluntary, and FWS is currently consulting with the applicant on the ideal timing for the permit, which will be issued after construction was initiated.
Target: 11/30/2017
Issuance of decision for permit/approval.
The Eagle Take Permit application for Phase 1 of the Chokecherry Sierra Madre Wind Energy Project is voluntary, and FWS is currently consulting with the applicant on the ideal timing for the permit, which will be issued after construction was initiated.
Target: 12/29/2017
Notice to proceed
Review Terminated with no decision