USA logoAn Official Website of the United States Government

You are here

Authorization for Liquefied Natural Gas Terminal Facilities, Onshore or in State Waters

Project Name: 
Status: 
In Progress
Responsible Agency: 
Federal Energy Regulatory Commission
Reason(s): 
Description: 

The Application to FERC has not been rendered complete for environmental purposes.  FERC has issued the follwoing information requests to the project sponsor to rectify an incomplete application. 

-Federal Energy Regulatory Commission, Environmental Data Request, (issued 7/5/17).  Document available at:  https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=14629422   

-Federal Energy Regulatory Commission, Environmental Data Request, (issued 7/28/17).  Document available at:  https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=14646029   

-Federal Energy Regulatory Commission, Environmental Data Request, (issued 8/31/17).  Document available at:  https://elibrary.ferc.gov/idmws/common/opennat.asp?fileID=14671341

Milestones:
Initial application received
Complete 04/17/2017
Completed application received
The Application to FERC has not been rendered complete for environmental purposes. FERC issued the data requests identified above in the description field to the project sponsor to rectify an incomplete application.
In Progress
Issuance of decision for permit/approval.
According to 18 C.F.R. § 3c.2(b), "The nature and time of any proposed action by the Commission are confidential and shall not be divulged to anyone outside of the Commission." However, The Application to FERC has not been rendered complete for environmental purposes. FERC issued the data requests identified above in the description field to the project sponsor to rectify an incomplete application. Each information request states that once we have received responses to all outstanding information requests and reviewed them for completeness, the Commission will establish a schedule for completing the EIS. After the EIS is complete, the Commission will be in a position to act on the application. Commission staff explains that once we have received responses to all outstanding information requests and reviewed them for completeness, the Commission will establish a schedule for completing the EIS.
In Progress
Notice to proceed
Review Terminated with no decision
N/A
Submit Feedback >