Authorization and Certification

Target Completion: 
06/30/2020
Status: 
Planned
Responsible Agency: 
Bureau of Saftey and Environmental Enforcemen
Agency Status: 
Cooperating under NEPA
Reason(s): 
Description: 

Bureau of Safety and Environmental Enforcement

Oil Spill Response Plan

Milestones:
Initial application received
Department of Interior
BSEE - Oil Spill Response Plan - Initial application received
Complete 03/03/2017
Completed application received
Hilcorp replied to BSEE's Requests for Additional Information on December 14. BSEE is reviewing the new submission.
In Progress
Target: 06/30/2017
Issuance of decision for permit/approval
Department of Interior
BSEE - Oil Spill Response Plan - Issuance of decision for approval
Planned
Target: 06/30/2020
Notice to proceed
N/A
Review Terminated with no decision
N/A