Navajo Gallup Water Supply Project

Navajo Gallup Water Supply Project (High Priority)

Coordinating Agency
Department of the Interior
Accountable POC
Lowell Pimley
Project Status
In Progress
Project Website
Google Map of Project
Description

The Navajo Gallup Water Supply Project is the cornerstone of the Navajo Nation water rights settlement in the San Juan River Basin in New Mexico, http://www.usbr.gov/uc/rm/navajo/nav-gallup/index.html. This water rights settlement Read More

Expedited Process

The Bureau of Reclamation is working to shorten the time needed to complete the federal actions necessary to proceed with project construction. For example, to expedite the process for gaining access to the area of the project known as Read More

Reviews, Approvals and Permits

Click on the Description Drop Down Arrow icon to view more information.
Title Responsible Agency Responsible Agency POC Name Target Completion Date Status Description Public Participation Address Public Participation Email Public Participation State Public Participation Website Public Participation Zip
Reach 12B ROW for Tribal Fee Lands: Final Action Department of the Interior R. Urbom 01/25/2013 Complete

Consent for Easement for Tribal Fee Lands is received and filed in the offical files.

Description Drop Down Arrow
Reach 12 Tohlakai Pumping Plant Right of Way for Construction on Tribal Fee Land State or Local Agency Jason John 02/06/2014 In Progress

Reach 12 Tohlakai Pumping Plant is located on the western, "San Juan Lateral" portion of the project. In order to award a construction contract for construction Reclamation must be granted permanent right of way and construction easements for all required property. Reclamation has worked with the Navajo Nation to obtain these documents on the Navajo Nation Tribal Fee Lands. Reclamation has coordinated and built relationships with the Navajo Nation to emphasize the high priority nature of the project and to expedite the Navajo Nations approval for consent process. Reclamation is working with the Navajo Nation to develop an expedited approval process on the remaining construction reaches for the project.

Description Drop Down Arrow
Reach 12B ROW for Tribal Fee Lands: Final ROW package received from The Navajo Nation and transmitted to BOR regional realty officer. Department of the Interior Micheal Braman 01/16/2013 Complete

The Bureau of Reclamation receives the Consent for Easement from The Navajo Nation and delivers to the Regional Realty Officer

Description Drop Down Arrow
Review Agreements Necessary to Begin Construction Department of the Interior Carter Brown 03/27/2012 Complete

Department of the Interior's Office of the Solicitor reviews documents necessary to meet conditions precedent to construction

Description Drop Down Arrow
Receive Offerors Proposal Department of the Interior Leslie Corpening 02/23/2012 Complete

This action includes the bid preparation or the proposal preparation process including site visit by the interested construction contractors (offerors).

Description Drop Down Arrow
REACH 22: Secure Executed "Programmatic Agreement Among Reclamation, ACHP, NMSHPO, Navajo Nation, BLM, and BIA..." Department of the Interior Joe Toumey 12/31/2011 Complete

The fully executed "Programmatic Agreement Among Reclamation, ACHP, NMSHPO, Navajo Nation, BLM, and BIA Regarding the Consideration and Management of Effects on Historic Properties Arising from Construction of the Navajo Gallup Water Supply Project, New Mexico" is required prior to BLM signing the "Decision Record for Design Data Collection on Reach 22 Lands, Administered by BLM".

Description Drop Down Arrow
REACH 22: Review and Sign "Decision Record for Design Data Collection on Reach 22 Lands, Administered by BLM" Department of the Interior Dave Evans 02/26/2012 Complete

Bureau of Land Management reviews and signs the "Decision Record for Design Data Collection on Reach 22 Lands, Administered by BLM".

Description Drop Down Arrow
REACH 22: Publish Notice of Availability of "Final Draft Environmental Assessment for Design Data Collection on Reach 22 Lands, Administered by BLM" Department of the Interior Gary Torres 01/17/2012 Complete

Bureau of Land Management will publish a notice of availability in the Federal Register and release "Final Draft Environmental Assessment for Design Data Collection on Reach 22 Lands, Administered by BLM" for public review and comment.

Description Drop Down Arrow
REACH 22: Prepare "Final Draft Environmental Assessment for Design Data Collection on Reach 22 Lands, Administered by BLM" Department of the Interior Molly Thrash 11/16/2011 Complete

Reclamation is assisting BLM in fulfilling its responsibilities for compliance with National Environmental Policy Act and other pertinent Federal laws and regulations. In that capacity, Reclamation will prepare the "Final Draft Environmental Assessment for Design Data Collection on Reach 22 Lands, Administered by BLM" to submit to Bureau of Land Management for review and action.

Description Drop Down Arrow
REACH 22: NHPA Section 106 Review by NM SHPO State or Local Agency Jan V. Biella 12/16/2011 Complete

In compliance with National Historic Preservation Act Section 106, the New Mexico State Historic Preservation Officer requires review and concurrance of the Final Cultural Resources Report regarding Design Data Collection for Reach 22 submitted by Reclamation.

Description Drop Down Arrow
REACH 22: NHPA Section 106 Consultations and Field Work Department of the Interior Joe Toumey 11/16/2011 Complete

In compliance with National Historic Preservation Act, Section 106, conduct consultations with Tribes that might attach religious or cultural significance to historic properties and other entities with regulatory, administrative, and/or management interests that may be affected by the project, and conduct field work . Reclamation will produce Final Cultural Resources Report.

Description Drop Down Arrow
REACH 22: Finalize the "Final Environmental Assessment for Design Data Collection on Reach 22 Lands, Administered by BLM" Department of the Interior Rob Waldman 02/18/2012 Complete

Reclamation is assisting BLM in fulfilling its responsibilities for compliance with National Environmental Policy Act and other pertinent Federal laws and regulations. In that capacity, Reclamation will review and address public comments on the Draft Environmental Assessment, address those comments, and finalize the "Environmental Assessment for Design Data Collection on Reach 22 Lands, Administered by BLM" to submit to BLM for review and action.

Description Drop Down Arrow
REACH 22: Approval of Application for Accessing BLM Lands (Standard Form 299) Department of the Interior Dave Evans 03/12/2012 Complete

Bureau of Land Management review and approval of "SF 299: Application for Transportation and Utility Systems and Facilities on Federal Lands" submitted by the Bureau of Reclamation.

Description Drop Down Arrow
REACH 22: Grant Right of Way for Design and Testing Surveys Department of the Interior Dave Evans 03/20/2012 Complete

Bureau of Land Management ย provides letter to Reclamation granting ย right of way to Reach 22 lands for the purpose of design and testing surveys.

Description Drop Down Arrow
Reach 22 Site Access for Design and Testing Surveys (REACH 22) Department of the Interior Brent Rhees 03/20/2012 Complete

Reach 22 is located on the eastern, Cutter Lateral portion of the project. In order to begin construction of Reach 22, Reclamation must obtain certain approvals to conduct surveys of the property needed for the pipeline and to evaluate the impacts of the project construction on cultural and historic resources. Reclamation has worked directly with each entity that will be involved with pre-construction activities to emphasize the high priority of the project. Reclamation is providing assistance with the BLM's Environmental Assessment for design data collection in Reach 22.

COMPLETION SUMMARY: The process for Reach 22 involved 9 individual actions. Action was required from the following agencies: Reclamation, State of New Mexico Historic Preservation Office and the BLM. COMPLETED January 30, 2012.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Support Resolution State or Local Agency K. Bennaly 12/06/2012 Complete

The Navajo Nation Resources Committee passes the support resolution for the final Right of Way Application Package.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Signature of Consent Letter State or Local Agency H. Anderson 12/28/2012 Complete

The Navajo Nation Office of the President/Vice President signs the letter of consent to grant the Right of Way for Reach 12B.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Review ROW Application Package State or Local Agency H. Draper 07/27/2012 Complete

The Reach 12B Right of Way Application Package for Tribal Trust and Fee Lands is received from the Bureau of Reclamation and is reviewed for completeness by the Navajo Nation Division of Natural Resources Land Department.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust Lands: Review ROW Application Package Department of the Interior J. Ration 02/22/2013 Complete

Department of Interior's Office of the Solicitor reviews the Right of Way Application Package and the Tribal Consent Documents.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust Lands: Receive ROW Application Package from BOR Department of the Interior J. Ration 01/25/2013 Complete

The Bureau of Indian Affairs receives the Right of Way Application Package for Tribal Trust Lands and Tribal Consent documents from the Bureau of Reclamation and performs preliminary review.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Project Field Clearance State or Local Agency H. Draper 07/27/2012 Complete

The Navajo Nation Land Department collects all required consent signatures and prepares support resolutions for the Resource Committee.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Prepare ROW package and deliver to NN Department of the Interior Michael Braman 01/09/2012 Complete

The Bureau of Reclamation prepares the complete Right of Way Application Package for Tribal Trust Lands and delivers to the Navajo Nation for review and consent for Right of Way.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Navajo Nation consent State or Local Agency F. White 01/07/2013 Complete

The Navajo Nation completes the Signature Authorization Sheet review process and submits a letter of consent for the Right of Way for Tribal Trust and Fee Lands to the Bureau of Reclamation.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Hazmat Assessment Department of the Interior Darryl Good 04/30/2012 Complete

A Reclamation certified Hazmat official inspects the Right of Way in accordance with American Society for Testing and Materials standards and performs the required testing to certify the absence of hazardous materials.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust Lands: Final ROW package received from NN and prepare ROW package and deliver to BIA Department of the Interior Michael Braman 01/16/2013 Complete

The Bureau of Reclamation receives consent for Right of Way from the Navajo Nation and prepares the complete Right of Way package to deliver to the Bureau of Indian Affairs for review and authorization for Right of Way.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust Lands: Final Review of Application for ROW Department of the Interior J. Ration 02/22/2013 Complete

The Bureau of Indian Affairs conducts a final review of the Right of Way Application Package and Tribal Consent documents.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust Lands: Final Approval of Application for ROW Department of the Interior S. Pinto 03/01/2013 Complete

Bureau of Indian Affairs approves the Grant of Easement for Right of Way for Reach 12B for Tribal Trust Lands and sends to the Bureau of Reclamation.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust Lands: Final Action Department of the Interior R. Urbom 03/18/2013 Complete

Grant of Easement for Tribal Trust Lands is received and filed in the official files

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust Lands: BIA Grant of Easement for ROW received from BIA, reviewed and transmitted to BOR Regional Realty officer Department of the Interior Michael Braman 03/12/2013 Complete

The Bureau of Reclamation receives the approved Grant of Easement from the Bureau of Indian Affairs and reviews and delivers to the Regional Realty officer.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve ROW Package State or Local Agency R. Das 10/19/2012 Complete

The Navajo Nation Minerals Department evaluates the value of right of way, reviews the final Right of Way Application Package, and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve ROW Package State or Local Agency P. Kyselka 10/11/2012 Complete

The Navajo Nation Fish and Wildlife Department reviews the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve ROW Package State or Local Agency M. Kahn 11/05/2012 Complete

The Navajo Nation Office of Legislative Services reviews the final Right of Way Application Package and sponsors the Resource Committee support resolution.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve ROW Package State or Local Agency B. Becker 09/28/2012 Complete

The Navajo Nation Office of the Attorney General conducts legal sufficiency review of the final Right of Way Application Package and signs the Signature Autorization Sheet.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve ROW Package State or Local Agency F. White 10/24/2012 Complete

The Navajo Nation Division of Natural Resources reviews the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve ROW Package State or Local Agency A. Downer 10/16/2012 Complete

The Navajo Nation Historic Preservation Department reviews the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve ROW Package State or Local Agency M. Halona 10/05/2012 Complete

The Navajo Nation Land Department reviews the final Right of Way Application Package and signs the Signature Autorization Sheet.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve ROW Package State or Local Agency H. Anderson 10/10/2012 Complete

The Navajo Nation Office of the President/Vice President reviews the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve ROW Package State or Local Agency R. Whitehorse Larsen 09/25/2012 Complete

The Navajo Nation Environmental Protection Agency conducts federal National Environmnetal Policy Act and Navajo Nation Environmental Protection Agency compliance review of the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve Cultural Resource Clearance Form State or Local Agency A. Downer 09/04/2012 Complete

The Navajo Nation Historic Preservation Department approves the Cultural Resource Clearance Form.

Description Drop Down Arrow
REACH 12B ROW for Tribal Trust and Fee Lands: Approve Biological Resource Clearance Form State or Local Agency G. Tom 09/04/2012 Complete

The Navajo Nation Fish and Wildlife Department approves the Biological Resource Clearance Form.

Description Drop Down Arrow
Reach 12B Right of Way for Construction on Navajo Nation Tribal Trust and Fee Lands and Fee (REACH 12B ROW on Tribal Trust and Fee Lands) Department of the Interior Brent Rhees 03/18/2013 Complete

Reclamation developed a construction schedule for the Navajo Gallup Water Supply Project which includes several "reaches" of pipeline construction. "Reach 12B" is located on the western, "San Juan Lateral" portion of the project. In order to award a construction contract and issue a notice to proceed for construction of Reach 12B, Reclamation must be granted permanent right of way and construction easements for all required property. Reclamation has worked with the Navajo Nation and Bureau of Indian Affairs (BIA) to obtain these documents on Navajo Nation Tribal Trust and Fee Lands. Reclamation has coordinated and built relationships with the Navajo Nation and BIA to emphasize the high priority nature of the project and to expedite both the Navajo Nation's approval for consent process and the BIA's right of way approval process. Reclamation is working with the Navajo Nation to develop an expedited approval process on the remaining construction reaches for the project.

Description Drop Down Arrow
Reach 12a Solicitation/Procurement Department of the Interior Brent Rhees 04/13/2012 Complete

"Reach 12a" is located on the western, "San Juan Lateral" portion of the project. Reclamation will post through the Federal Business Opportunities website the solicitation for the construction work. Reclamation will receive the offerors competitive proposals and thoroughly analyze the offerors proposals utilizing the Technical Proposal Evaluation Committee (TPEC) process. Reclamation will negotiate and award a contract for construction to the offeror that provides the best value to the federal government.

COMPLETION SUMMARY: The process for Reach 12A Solicitation/Procurement involved 4 individual actions. Action was required from the Reclamation Four Corners Construction Office (FCCO) and the Reclamation Contracting Officer. The process began with FCCO gathering and reviewing all the documents required for bidding. The Contracting Officer issued the solicitation for bid, received bids and awarded the contract for construction. COMPLETED April 16, 2012.

Description Drop Down Arrow
REACH 12a ROW: Support Resolution State or Local Agency K. Benally 03/30/2012 Complete

The Navajo Nation Resources Committee passes the support resolution for the final Right of Way Application Package.

Description Drop Down Arrow
REACH 12a ROW: Submit ROW Application Package Department of the Interior S. Jones 04/19/2012 Complete

Reclamation submits Right of Way Application Package and Tribal consent documents to Bureau of Indian Affairs.

Description Drop Down Arrow
REACH 12a ROW: Sign Consent Letter State or Local Agency H. Anderson 04/04/2012 Complete

The Navajo Nation President/Vice President signs letter of consent to grant the Right of Way for Reach 12a.

Description Drop Down Arrow
REACH 12a ROW: Review ROW Application Package State or Local Agency Howard Draper 05/24/2011 Complete

The Reach 12a Right of Way Application Package submittal is reviewed for completeness by the Navajo Nation Division of Natural Resources Land Department.

Description Drop Down Arrow
REACH 12a ROW: Review ROW Application Package Department of the Interior S. Jones 05/01/2012 Complete

Department of the Interior's Office of the Solicitor reviews Right of Way Application Package and Tribal consent documents.

Description Drop Down Arrow
REACH 12a ROW: Project Field Clearance State or Local Agency H. Draper 11/07/2011 Complete

The Navajo Nation Land Department collects all required consent signatures and prepares support resolutions for the Resources Committee.

Description Drop Down Arrow
REACH 12a ROW: Navajo Nation Consent State or Local Agency F. White 04/06/2012 Complete

The Navajo Nation completes the Signature Authorization Sheet review process and submits the final Right of Way Application Package to Reclamation.

Description Drop Down Arrow
REACH 12a ROW: Hazmat Assessment Department of the Interior B. Longwell 06/01/2012 Complete

A Reclamation Hazardous Materials certified official inspects the Right of Way in accordance with American Society for Testing and Materials standards and performs required testing to certify the absence of hazardous materials.

Description Drop Down Arrow
REACH 12a ROW: Final Review of ROW Application Department of the Interior S. Jones 05/14/2012 Complete

In coordination with the Office of the Solicitor, the Bureau of Indian Affairs conducts final review of Right of Way Application Package and Tribal consent documents.

Description Drop Down Arrow
REACH 12a ROW: Final Approvals Navajo Nation Tribal Trust Lands Department of the Interior J. Roundy 06/29/2012 Complete

Grant of Easement for Tribal Tust Lands is received and filed in the official files.

Description Drop Down Arrow
REACH 12a ROW: Final Approval of Application for ROW Department of the Interior S. Pinto 05/17/2012 Complete

Bureau of Indian Affairs approves the Right of Way for Reach 12a.

Description Drop Down Arrow
REACH 12a ROW: Approve ROW Package State or Local Agency B. Becker 01/03/2012 Complete

e Navajo Nation Office of the Attorney General conducts legal sufficiency review of the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12a ROW: Approve ROW Package State or Local Agency F. White 12/27/2011 Complete

The Navajo Nation Division of Natural Resources reviews the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12a ROW: Approve ROW Package State or Local Agency A. Downer 12/13/2011 Complete

The Navajo Nation Historic Preservation Department reviews the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12a ROW: Approve ROW Package State or Local Agency M. Halona 11/18/2011 Complete

The Navajo Nation Land Department reviews the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12a ROW: Approve ROW Package State or Local Agency H. Anderson 01/05/2012 Complete

The Navajo Nation Office of the President/Vice President reviews the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12a ROW: Approve ROW Package State or Local Agency R. Whitehorse Larsen 12/29/2011 Complete

The Navajo Nation Environmental Protection Agency conducts federal National Environmental Policy Act and Navajo Nation Environmental Protection Agency compliance review of the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12a ROW: Approve ROW Package State or Local Agency R. Das 12/20/2011 Complete

The Navajo Nation Minerals Department evaluates the value of right of way, reviews the final Right of Way Application Package, and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12a ROW: Approve ROW Package State or Local Agency P. Kyselka 12/12/2011 Complete

The Navajo Nation Fish and Wildlife Department reviews the final Right of Way Application Package and signs the Signature Authorization Sheet.

Description Drop Down Arrow
REACH 12a ROW: Approve ROW Package State or Local Agency M. Kahn 01/13/2012 Complete

The Navajo Nation Office of Legislative Services reviews the final Right of Way Application Package, signs the Signature Authorization Sheet, and sponsors the Resources Committee support resolution.

Description Drop Down Arrow
REACH 12a ROW: Approve Cultural Resource Clearance Form State or Local Agency Alan Downer 05/11/2011 Complete

The Navajo Nation Historic Preservation Department approves the Cultural Resource Clearance Form.

Description Drop Down Arrow
REACH 12a ROW: Approve Biological Resource Clearance Form State or Local Agency G. Tom 05/11/2011 Complete

Navajo Nation Fish and Wildlife Department approves the Biological Resource Clearance Form.

Description Drop Down Arrow
Reach 12A Right of Way for Construction Tribal Trust Lands (REACH 12A ROW) Department of the Interior Brent Rhees 06/29/2012 Complete

"Reach 12A" is located on the western, "San Juan Lateral" portion of the project. In order to award a construction contract and issue a notice to proceed for construction of Reach 12A, Reclamation must be granted permanent right of way and construction easements for all required property. Reclamation has coordinated and built relationships with the Navajo Nation and BIA to emphasize the high priority nature of the project and to expedite both the Navajo Nation's approval for consent process and the BIA's right of way approval process.

COMPLETION SUMMARY: The process for Reach 12A ROW for Construction involved 22 individual actions. Action was required from The Navajo Nation, Reclamation and the BIA. The Navajo Nation actions uses the process refered to as the Signature Authorization Sheet (SAS) and required action from 11 different Navajo Nation governmental offices. COMPLETED: June 21, 2012.

Description Drop Down Arrow
Programmatic Agreement Signatory Process; Final Signature Advisory Council on Historic Preservation Tom McCulloch, PhD 12/31/2011 Complete

Advisory Council on Historic Preservation signs the "Programmatic Agreement Among Reclamation, ACHP, NMSHPO, Navajo Nation, BLM, and BIA Regarding the Consideration and Management of Effects on Historic Properties Arising from Construction of the Navajo Gallup Water Supply Project, New Mexico" after it is signed by all other signatories.

Description Drop Down Arrow
Programmatic Agreement Signatory Process Department of the Interior Dave Evans 12/01/2011 Complete

Bureau of Land Management signs the "Programmatic Agreement Among Reclamation, ACHP, NMSHPO, Navajo Nation, BLM, and BIA Regarding the Consideration and Management of Effects on Historic Properties Arising from Construction of the Navajo Gallup Water Supply Project, New Mexico".

Description Drop Down Arrow
Programmatic Agreement Signatory Process Department of the Interior Carol DeAngelis 12/01/2011 Complete

Reclamation signs the "Programmatic Agreement Among Reclamation, ACHP, NMSHPO, Navajo Nation, BLM, and BIA Regarding the Consideration and Management of Effects on Historic Properties Arising from Construction of the Navajo Gallup Water Supply Project, New Mexico" and coordinates the signing by other signatories.

Description Drop Down Arrow
Programmatic Agreement Signatory Process State or Local Agency Jan V. Biella 12/01/2011 Complete

New Mexico State Historic Preservation Officer signs the "Programmatic Agreement Among Reclamation, ACHP, NMSHPO, Navajo Nation, BLM, and BIA Regarding the Consideration and Management of Effects on Historic Properties Arising from Construction of the Navajo Gallup Water Supply Project, New Mexico".

Description Drop Down Arrow
Programmatic Agreement Signatory Process Department of the Interior Terry McClung 12/01/2011 Complete

Bureau of Indian Affairs signs the "Programmatic Agreement Among Reclamation, ACHP, NMSHPO, Navajo Nation, BLM, and BIA Regarding the Consideration and Management of Effects on Historic Properties Arising from Construction of the Navajo Gallup Water Supply Project, New Mexico".

Description Drop Down Arrow
Programmatic Agreement Signatory Process State or Local Agency Dr. Alan Downer 12/01/2011 Complete

Navajo Nation Tribal Historic Preservation Officer signs the "Programmatic Agreement Among Reclamation, ACHP, NMSHPO, Navajo Nation, BLM, and BIA Regarding the Consideration and Management of Effects on Historic Properties Arising from Construction of the Navajo Gallup Water Supply Project, New Mexico".

Description Drop Down Arrow
Issue Solicitation Department of the Interior Leslie Corpening 02/16/2012 Complete

Includes advertisement for bid or request for proposals from construction contractors (offerors).

Description Drop Down Arrow
Execute Agreements Necessary to Begin Construction Department of the Interior Larry Walkoviak 04/11/2012 Complete

Bureau of Reclamation executes documents necessary to meet conditions precedent to construction.

Description Drop Down Arrow
REACH 22: Grant Right of Way for Design and Testing Surveys Department of the Interior Dave Evans 03/20/2012 Complete

Bureau of Land Management provides letter to Reclamation granting right of way to Reach 22 lands for the purpose of design and testing surveys.

Description Drop Down Arrow
Documents submitted from FCCF Department of the Interior Barry Longwell 10/07/2011 Complete

Gather and review all documents required for bid

Description Drop Down Arrow
Construction Contracts Award Process Department of the Interior Leslie Corpening 04/13/2012 Complete

Bureau of Reclamation will advertise, review, negotiate, and award construction contracts.

Description Drop Down Arrow
Complete Project Pre-Construction Activities Department of the Interior Ed Warner 03/20/2012 Complete

In addition to the specific activities relating to Reach 22 and other reaches, Reclamation will work with the Advisory Council on Historic Preservation, New Mexico State Historic Preservation Officer, Navajo Nation, Bureau of Land Management, and Bureau of Indian Affairs to execute a Programmatic Agreement that governs the evaluation of the effects of project construction on historic and culturally important properties.

COMPLETION SUMMARY: The process for the Completion of Project Pre-Construction Activities involved the execution of 3 separate agreements/contracts including the Programmatic Agreement, the City of Gallup and the Jicarilla Apache Nation Repayment Contracts. Input and action was required from the following agencies: Reclamation, BIA, BLM, The Navajo Nation, The State of New Mexico Historic Preservation Office, Advisory Council on Historic Preservation, DOI Solicitor, the City of Gallup and the Jicarilla Apache Nation. COMPLETED April 16, 2012.

Description Drop Down Arrow
Award Department of the Interior Leslie Corpening 04/13/2012 Complete

This action includes evaluation of the bids or proposals and the final selection of the successful offeror and approval of all bid and performance bonds.

Description Drop Down Arrow