Miami Harbor

Miami Harbor (Nationally or Regionally Significant Projects)

Coordinating Agency
Department of Defense
Accountable POC
Doris Valentin-Meyer
Project Status
Complete
Description
The Army Corps is working with the Port of Miami to construct an authorized project that involves deepening the Federal navigation at the port from its current depth of 42 feet to a depth of 50 feet. The project would enable the port to Read More

Reviews, Approvals and Permits

Click on the Description Drop Down Arrow icon to view more information.
Title Responsible Agency Responsible Agency POC Name Target Completion Date Status Description Public Participation Address Public Participation Email Public Participation State Public Participation Website Public Participation Zip
Project Partnership Agreement (PPA) Execution Department of Defense Doris Valentin-Meyer 08/15/2012 Complete

The PPA is a legally binding agreement between the Government and a non-Federal sponsor (state, port authority, etc.) for the construction of a water resources project. It describes the project and the responsibilities of the Government and the non-Federal sponsor in the cost sharing and execution of work. The PPA must be executed prior to the beginning of construction and allows us to accept the non-Federal sponsor's funds to accomplish this work.

Description Drop Down Arrow
Ocean Dredged Material Disposal Site permit issued Environmental Protection Agency Doris Valentin-Meyer 12/01/2011 Complete

The Environmental Protection Agency issues this permit to allow suitable dredged material to be placed in a designated ocean disposal site.

Description Drop Down Arrow
Issuance of the Record of Decision Department of Defense--Military Programs Doris Valentin-Meyer 05/22/2006 Complete

Record of Decision on the proposed project.

Description Drop Down Arrow
BCOE Certification Department of Defense Doris Valentin-Meyer 07/27/2012 Complete

Biddability, constructability, operability, and environmental certification that is performed as part of the finalization of the procurement documents that will be used to advertise the construction contract.

Description Drop Down Arrow
Water Quality Certification Permit issued Environmental Protection Agency Doris Valentin-Meyer 05/22/2012 Complete

The water quality certification permit is issued by the State under Section 401 of the Clean Water Act. The permit is issued by the state to regulate activities that will result in the discharge of dredged material into navigable waters.

Description Drop Down Arrow