Devil's Lake Rail Improvements

Devil's Lake Rail Improvements (Nationally or Regionally Significant Projects)

Coordinating Agency
Department of Transportation
Accountable POC
Andrea Martin
Project Status
Complete
Description
The Project will address rising level of Devil's Lake that floods the BNSF rail line between Devil's Lake and Church's Ferry, North Dakota. The Project will ensure the rail line remains open to passenger and freight traffic, and avoids Read More

Reviews, Approvals and Permits

Click on the Description Drop Down Arrow icon to view more information.
Title Responsible Agency Responsible Agency POC Name Target Completion Date Status Description Public Participation Address Public Participation Email Public Participation State Public Participation Website Public Participation Zip
404 Permit Review and Ongoing Mitigation Site Monitoring Department of Defense Jason Renschler 10/31/2012 Complete

BNSF/North Dakota DOT will submit a juisdictional delineation and a 404 permit application for Devils Lake Grade Raise Project to the U.S. Army Corps of Engineers (US ACE). US ACE will complete the 404 permitting process in 45-days from when they determine if the permit application is complete. Although, if the impacts to wetlands are found to be greater than .5 acres, US ACE will have to coordinate with other agencies (EPA, US FWS, etc) if these groups present reasonable objection to the use of a NWP 3, then the US ACE will have to prepare an individual permit. An individual permit takes about 120 days to issue.

Description Drop Down Arrow
NEPA Determination Department of Transportation Andrea Martin 10/01/2012 Complete

Federal Railroad Administration will make an environmental determination and complete the NEPA process if the project qualifies for a categorical exclusion. An environmental assessment for this project would need a minimum of six months to complete from June 13, 2012.

FRA received environmental documentation from the Project Sponsor on 09/14/2012, processed and approved a categorical exclusion for Phase 2 of the Project on 09/27/2012.