Dakota Prairie Grasslands

Dakota Prairie Grasslands (High Priority)

Coordinating Agency
Department of Agriculture
Accountable POC
Barry Burkhardt
Project Status
Complete
Google Map of Project
Description
USDA Forest Service (FS) is working under an expedited process to review oil and gas applications for wells and ancillary facilities (such as pipelines and power lines) in the Dakota Prairie Grasslands. Approximately 80 applications have Read More
Expedited Process

USDA Forest Service is working under an expedited process to review oil and gas applications for wells and supporting facilities (such as pipelines and power lines) in the Dakota Prairie Grasslands. There are approximately 80 Read More

Reviews, Approvals and Permits

Click on the Description Drop Down Arrow icon to view more information.
Title Responsible Agency Responsible Agency POC Name Target Completion Date Status Description Public Participation Address Public Participation Email Public Participation State Public Participation Website Public Participation Zip
NEPA Compliance Department of Agriculture Barry Burkhardt 12/06/2011 Complete

Review the proposal relative to Section 390 Categorical Exclusion or initiate environmental analysis.

Description Drop Down Arrow
Surface Use Plan of Operations (SUPO) Approval Department of Agriculture Barry Burkhardt 12/11/2011 Complete

Approve Surface Use Plan of Operation with Conditions of Approval if needed

Description Drop Down Arrow
Application for Permit to Drill (APD) Approval Department of the Interior Lonny Bagely 12/16/2011 Complete

Incorporate Surface Use Plan of Operations (SUPO) approval and Aprove the Application for Permit to Drill

Description Drop Down Arrow
Receive Application for Permit to Drill (APD) and determine complete Department of Agriculture Barry Burkhardt 10/07/2011 Complete

Review the Surface Use Plan of Operation for compliance with Onshore Order No. 1

Review the Surface Use Plan of Operation for compliance with Onshore Order No. 1

Description Drop Down Arrow