NEPA Determination

NEPA Determination

Project Title
Devil's Lake Rail Improvements
Type
Activity
Status
Complete
Responsible Agency
Department of Transportation
Responsible Agency POC Name
Andrea Martin
Responsible Agency POC Title
Environmental Protection Specialist
Responsible Agency POC Email
andrea.martin@dot.gov
Target Start Date
08/06/2012
Target Completion Date
10/01/2012
Actual Start Date
09/14/2012
Actual Completion Date
09/27/2012
Potential Obstacles/ Delays
None. Limited construction season in North Dakota.
Last Updated On
05/22/2013
Description
Federal Railroad Administration will make an environmental determination and complete the NEPA process if the project qualifies for a categorical exclusion. An environmental assessment for this project would need a minimum of six months to complete from June 13, 2012.

FRA received environmental documentation from the Project Sponsor on 09/14/2012, processed and approved a categorical exclusion for Phase 2 of the Project on 09/27/2012.