Project Title
Crenshaw/LAX
Type
Activity
Status
Complete
Responsible Agency
Department of Transportation
Responsible Agency POC Name
Benito DeLeon
Responsible Agency POC Title
Director, Office of Planning and Programming
Responsible Agency POC Email
Benito.DeLeon@faa.gov
Target Start Date
10/04/2011
Target Completion Date
02/29/2012
Actual Start Date
10/04/2011
Actual Completion Date
02/29/2012
Last Updated On
05/23/2013
Description
The Federal Aviation Administration (FAA) has responsibility to promote air safety and the efficient use of the navigable airspace, therefore any project that would construct or alter infrastructure on or near an airport must notify the FAA by submitting a Form 7460. The Form 7460 is the formal process the FAA uses to conduct interagency evaluations of proposals for construction of new infrastructure projects at or near airports and to determine whether the proposed development meets certain FAA standards that ensure safety and efficiency.
The LA Metro office submitted the appropriate 7460 application forms for the Crenshaw/LAX line proposal to the FAA in October 2011. The FAA is currently conducting an internal review of the applications and is on schedule to complete its review by the February 2012 target date.