Project Title
BakkenLink Crude Oil Pipeline
Type
Activity
Status
Complete
Responsible Agency
Department of the Interior
Responsible Agency POC Name
Lowell Hassler
Target Start Date
09/28/2012
Target Completion Date
10/15/2012
Actual Start Date
09/28/2012
Actual Completion Date
10/22/2012
Last Updated On
05/20/2013
Description
FONSI/Notice to Proceed was signed by the BLM, North Dakota Field Manager 10-22-12.